← Back to Market Insights
Market Insights Jan 28, 2026 4 min read Georgia Ports Authority

Port Drayage Alert: Savannah GPA Phase III Construction Starting H2 2026

The Georgia Ports Authority Phase III crane installation begins in July 2026. Expected drayage rate increases of 6–9% as port operations face temporary disruptions and capacity constraints.

+6–9% Expected Drayage Rate Increase GPA Phase III impact estimate
H2 2026 Phase III Start Date GPA Official Timeline
+1.2M TEUs Annual Throughput Increase by 2028 GPA Capacity Model

Savannah Port Phase III: Construction Timeline & Impact

The Georgia Ports Authority's Phase III expansion—a $1.3 billion investment in cranes, dock infrastructure, and rail capacity—officially breaks ground in July 2026. The project spans 24–30 months and will eventually add 1.2 million TEU of annual throughput to Savannah's already busy Port of Savannah, making it the third-largest U.S. container port by capacity.

But construction comes with near-term pain. Drayage carriers operating on the Savannah to inland Georgia/Florida distribution network will face:

  • Port congestion during crane installation (July–October 2026)
  • Lane closures and realignment of container yard operations
  • Capacity constraints on inbound/outbound drayage movements
  • Temporary diversions to competing ports (Charleston, Jacksonville) likely to ease congestion

These constraints will push drayage rates 6–9% above baseline. For a shipper with 500 FEU movements annually through Savannah (import and export combined), a 6–9% rate increase translates to $15,000–$22,500 in additional annual cost.

Action item: Lock drayage contracts now (Q1 2026) for H2 2026–Q1 2027 before carriers adjust rates upward in anticipation of Phase III construction. Rates locked in March–April will protect you through the construction window.

Phase III Timeline & Capacity Impact

Phase Timeline Drayage Impact Recommendation
Phase III Groundbreaking July 2026 Initial congestion, rate pressure begins Lock Q3 contracts before July
Crane Installation July–December 2026 Peak congestion, +6–9% rates Budget for rate increase, consider routing to CSX rail
Dock Reconfiguration Q1–Q2 2027 Operational disruptions continue Maintain alternative routing options
Stabilization & Ramp-Up Q3–Q4 2027 Rates normalize, capacity improves Expect 5–10% rate relief as efficiency improves
Phase III Complete Q2–Q3 2028 +18% sustained capacity, competitive drayage Long-term cost benefit materializes

Which Shippers Are Most Affected?

High-volume Savannah port users face the biggest exposure:

  • High volume at Savannah (1,000+ FEU annually): Cost exposure $30,000–$60,000 over the construction window
  • Apparel/consumer goods importers: Asia-to-Savannah routes will see elevated congestion during peak fall/winter months (Aug–Nov 2026)
  • Export agricultural freight: Perishables requiring rapid gate turnaround will face delays during yard reconfigurations
  • Regional LTL/drayage operators: Margin compression as Savannah port costs rise and competitive routing to Charleston becomes necessary

Shippers with flexible routing (e.g., willing to use Charleston Port or Jacksonville Port during construction) can mitigate cost impact by diversifying in H2 2026.

Strategic Responses: Three Options

Option 1: Lock Savannah Drayage Contracts Now. Negotiate 12-month rates for Savannah drayage covering H2 2026–H1 2027. Current rates ($185–$220 per FEU for typical moves) are at baseline. Lock them before carriers begin surcharging for construction.

Option 2: Shift Volume to Alternative Ports. Charleston (CHS) and Jacksonville (JAX) drayage rates are currently comparable to Savannah. Consider balancing port utilization to reduce Savannah exposure during the construction window. JAX has particularly favorable container handling and rail connectivity through CSX.

Option 3: Negotiate GRI Deferral Clauses. Propose a contract amendment capping drayage rate adjustments (GRI) at 3–4% through Q4 2026, then resuming normal escalation in 2027. Carriers may accept this for committed volume.

Savannah Port Phase III Impact

Construction Start:
July 2026
Expected Drayage Increase:
+6–9%
Current Drayage Rate:
$185–$220/FEU
Construction Window:
July 2026–Q2 2027
Annual Impact (500 FEU):
+$15,000–$22,500
Normalization Timeline:
Q3–Q4 2027

Key Takeaways

  • Georgia Ports Authority Phase III construction begins July 2026 and will disrupt Savannah port operations for 24–30 months
  • Expect drayage rates to increase 6–9% during the construction window; shippers with 500+ annual FEU movements will see $15K–$22.5K cost exposure
  • Lock Savannah drayage contracts before June 2026 to secure baseline rates; delays risk carrying construction surcharges through H2 2026
  • Alternative routing to Charleston and Jacksonville offers similar rates and may reduce construction-related congestion exposure
  • Phase III completion in Q2–Q3 2028 will add 1.2M TEU annual capacity and drive long-term drayage competition and cost relief